🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · WEST

Ne100S

Ne100S is a 100 MW solar request with a signed interconnection agreement in the West interconnection queue, in El Paso County, Texas, connecting to El Paso Electric Company.

Queue statusConsented
  1. PlanningQueued Mar 2024 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
LG-24-3-8
Grid region
West (non-ISO utilities)
Utility / transmission owner
El Paso Electric Company
Connection point (POI)
Patriot 115 kV Substation
Location
El Paso County, Texas
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
LGIA EXECUTED
Queue status
Active
Entered queue
27 March 2024
Proposed online date
February 2027

Location

Marker shows the centre of El Paso County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in El Paso County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem