🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Loma Pinta Wind

Loma Pinta Wind is a 197 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in La Salle County, Texas.

Queue statusConsented
  1. PlanningQueued May 2015 (completed)
  2. ConsentedDec 2017 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
16INR0112
Grid region
ERCOT (Texas)
Developer
Enerverse
Connection point (POI)
5705 Fowlerton 138kV
Location
La Salle County, Texas
Technology
Wind: 197 MW
Total requested
197 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
18 May 2015
Agreement signed
13 December 2017
Proposed online date
December 2026

Location

Marker shows the centre of La Salle County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in La Salle County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem