United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTLoma Pinta Wind
Loma Pinta Wind is a 197 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in La Salle County, Texas.
Queue statusConsented
- PlanningQueued May 2015 (completed)
- ConsentedDec 2017 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 16INR0112
- Grid region
- ERCOT (Texas)
- Developer
- Enerverse
- Connection point (POI)
- 5705 Fowlerton 138kV
- Location
- La Salle County, Texas
- Technology
- Wind: 197 MW
- Total requested
- 197 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 18 May 2015
- Agreement signed
- 13 December 2017
- Proposed online date
- December 2026
Location
Marker shows the centre of La Salle County; the queue data does not give exact sites.
Other requests in La Salle County
- La Salle SolarSolar · 513 MW · agreement signed
- Cotulla BESS 1Battery storage · 9.9 MW · agreement signed
- Crescent C BESSBattery storage · 508 MW · in study
- Vazlon Solar SLFSolar + storage · 211 MW · in study
- Revolution BESSBattery storage · 209 MW · in study
- Loma Pinta SolarSolar · 203 MW · in study
- Dahlia SolarSolar · 201 MW · in study
- Hinkell BESSBattery storage · 78.1 MW · in study
- Holcomb BESS (Burro BESS)Other · 10.0 MW · built
- Loma Pinta IIOnshore wind · 202 MW · withdrawn
- Zircon BESSBattery storage · 80.4 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem