🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Hinkell BESS

Hinkell BESS is a 78.1 MW battery storage request in interconnection study in the ERCOT interconnection queue, in La Salle County, Texas.

Queue statusIn planning
  1. PlanningQueued Aug 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0395
Grid region
ERCOT (Texas)
Developer
Reveille BESS
Connection point (POI)
8612 Reveille 138kV
Location
La Salle County, Texas
Technology
Battery: 78.1 MW
Total requested
78.1 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
21 August 2023
Proposed online date
July 2027

Location

Marker shows the centre of La Salle County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in La Salle County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem