United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Cotulla BESS 1

Cotulla BESS 1 is a 9.9 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in La Salle County, Texas.

Queue statusConsented
  1. Planning (completed)
  2. ConsentedApr 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0638
Grid region
ERCOT (Texas)
Developer
SBESS TX19 LLC
Connection point (POI)
Cotulla Substation XFMR 2 #460 CKT Sub max transmission - 138kv Substation name - COTULLA Bus # 8610 Load - LOAD02
Location
La Salle County, Texas
Technology
Battery: 9.9 MW
Total requested
9.9 MW
Study phase
IA Executed
Queue status
Active
Agreement signed
15 April 2024
Proposed online date
April 2026

Location

Marker shows the centre of La Salle County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in La Salle County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem