Tres Bahias Solar

Tres Bahias Solar is a 195 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Calhoun County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2019 (completed)
  2. ConsentedAug 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0266
Grid region
ERCOT (Texas)
Developer
Tres Bahias Solar Power LLC
Connection point (POI)
8140 Joslin 138kV
Location
Calhoun County, Texas
Technology
Solar: 195 MW
Total requested
195 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
26 March 2019
Agreement signed
7 August 2020
Proposed online date
December 2025

Location

Marker shows the centre of Calhoun County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Calhoun County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem