United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTTres Bahias Solar
Tres Bahias Solar is a 195 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Calhoun County, Texas.
Queue statusConsented
- PlanningQueued Mar 2019 (completed)
- ConsentedAug 2020 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 20INR0266
- Grid region
- ERCOT (Texas)
- Developer
- Tres Bahias Solar Power LLC
- Connection point (POI)
- 8140 Joslin 138kV
- Location
- Calhoun County, Texas
- Technology
- Solar: 195 MW
- Total requested
- 195 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 26 March 2019
- Agreement signed
- 7 August 2020
- Proposed online date
- December 2025
Location
Marker shows the centre of Calhoun County; the queue data does not give exact sites.
Other requests in Calhoun County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem