VictPort

VictPort is a 100 MW gas request built and operating in the ERCOT interconnection queue, in Calhoun County, Texas.

Queue statusOperating
  1. PlanningQueued Apr 2016 (completed)
  2. ConsentedMar 2018 (completed)
  3. Construction (completed)
  4. OperatingJun 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
17INR0045
Grid region
ERCOT (Texas)
Developer
Castleman Power
Connection point (POI)
8143 Dupont 138kV
Location
Calhoun County, Texas
Technology
Gas: 100 MW
Total requested
100 MW
Study phase
IA
Queue status
Operational
Entered queue
19 April 2016
Agreement signed
6 March 2018
Proposed online date
September 2019
Came online
June 2019

Location

Marker shows the centre of Calhoun County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Calhoun County