πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OTHER Β· ERCOT

Canvasback II BESS

Canvasback II BESS is a 50.4 MW other request withdrawn in the ERCOT interconnection queue, in Calhoun County, Texas.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedJun 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0454
Grid region
ERCOT (Texas)
Developer
Black Mountain Energy Storage II
Connection point (POI)
8155 SANDCRAB4A
Location
Calhoun County, Texas
Technology
Other: 50.4 MW
Total requested
50.4 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Proposed online date
May 2025
Withdrawn
June 2024

Location

Marker shows the centre of Calhoun County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Calhoun County