United States › Grid › Interconnection queues › Indiana

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Indiana — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown30059.6 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

300 requests · page 2 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J3846, Newton County
Onshore wind
275 MWIn study Newton, INMISO Jan 2025target 2030
Madison County Combustion Turbine
Gas · Indiana Municipal Power Agency (IMPA)
268 MWIn study Anderson, INMISO Aug 2025target 2028
Mayapple Solar
Solar
260 MWAgreement signed Pulaski, INPJM Sep 2020target 2027
Vermilion Grove Wind
Onshore wind · Vermilion Grove Wind, LLC
255 MWIn study Vermillion, INPJM Sep 2019target 2022
Solar + storage project AH2-112, St. Joseph County
Solar + storage
250 MWIn study St. Joseph, INPJM Feb 2022target 2026
Solar project J2970, Posey County
Solar
250 MWIn study Posey, INMISO Sep 2022target 2026
Solar + storage project J3077, Gibson County
Solar + storage
250 MWIn study Gibson, INMISO Sep 2022target 2026
Replace 250MW of the existing Petersburg coal unit with PV and DC-coupled battery storage; Petersburg 2
Solar + storage
250 MWIn study Pike, INMISO Oct 2021target 2024
Solar project J829, Sullivan County
Solar
250 MWUnder construction Sullivan, INMISO Jun 2017target 2022
Battery storage project J2581, Ripley County
Battery storage
250 MWIn study Ripley, INMISO Sep 2022target 2026
Solar project AG2-029, Noble County
Solar · Southern Pike Solar LLC
250 MWIn study Noble, INPJM Feb 2025target 2024
Solar project AG2-163, Fountain County
Solar · Dolphin Solar LLC
250 MWIn study Fountain, INPJM Feb 2025target 2024
Solar project J2849, Pulaski County
Solar
245 MWIn study Pulaski, INMISO Sep 2022target 2025
Solar project J1067, Jasper County
Solar
240 MWUnder construction Jasper, INMISO Mar 20182024
Solar project J3495, Greene County
Solar
220 MWIn study Greene, INMISO Apr 2024target 2028
Solar project AG2-245, Starke County
Solar · STARKE CENTRAL PROJECT, LLC
210 MWIn study Starke, INPJM Mar 2025target 2023
Solar + storage project AH2-419, Laporte County
Solar + storage
210 MWIn study Laporte, INPJM Mar 2022target 2026
Honey Creek Solar
Solar + storage
200 MWAgreement signed White, INPJM Feb 2020target 2027
Solar project J2566, Daviess County
Solar
200 MWIn study Daviess, INMISO Sep 2022target 2026
Solar project J1616, Knox County
Solar
200 MWIn study Knox, INMISO Jun 2020target 2026
Solar project J1691, Sullivan County
Solar
200 MWIn study Sullivan, INMISO Jun 2020target 2026
Solar project J992, Cass County
Solar
200 MWUnder construction Cass, INMISO Mar 2018target 2023
Solar + storage project J3978, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Battery storage project J3291, Lagrange County
Battery storage
200 MWIn study Lagrange, INMISO Apr 2024target 2028
Onshore wind project J1069, Jasper County
Onshore wind
200 MWUnder construction Jasper, INMISO Mar 2018target 2023
Solar + storage project J3980, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Warren County Wind Energy Center
Onshore wind
200 MWAgreement signed INPJM Sep 2020target 2028
Battery storage project J2663, White County
Battery storage
200 MWIn study White, INMISO Sep 2022target 2026
Black Prairie Solar Park
Solar
200 MWAgreement signed White, INPJM Sep 2019target 2027
Solar project J2230, Sullivan County
Solar
200 MWIn study Sullivan, INMISO Mar 2022target 2025
Bottlebrush Solar
Solar
200 MWAgreement signed Lake, INPJM Jan 2019target 2028
Solar + storage project AH2-025, Fountain County
Solar + storage
200 MWIn study Fountain, INPJM Oct 2021target 2027
Solar project J1772, White County
Solar
200 MWIn study White, INMISO Jun 2020target 2026
Solar project J2538, Clark County
Solar
200 MWIn study Clark, INMISO Oct 2025target 2026
Battery storage project J2213, Marshall County
Battery storage
200 MWIn study Marshall, INMISO Mar 2022target 2028
Blackford Wind Energy Project
Onshore wind
200 MWAgreement signed Blackford, INPJM Sep 2019target 2026
Solar + storage project AI1-134, Grant County
Solar + storage
200 MWIn study Grant, INPJM Sep 2022target 2029
Trade Post Solar Energy Center
Solar
200 MWAgreement signed Sullivan, INPJM Mar 2017target 2026
Solar project J3719, Miami County
Solar
200 MWIn study Miami, INMISO Mar 2024target 2028
Solar project J1481, Howard County
Solar
200 MWAgreement signed Howard, INMISO Apr 2019target 2025
Solar + storage project J1642, Spencer County
Solar + storage
200 MWIn study Spencer, INMISO Feb 2022target 2023
Battery storage project J2472, Sullivan County
Battery storage
200 MWIn study Sullivan, INMISO Sep 2022target 2027
Solar project J993, Boone County
Solar
200 MWUnder construction Boone, INMISO Mar 2018target 2023
Solar project J1780, Montgomery County
Solar
200 MWIn study Montgomery, INMISO Jun 2020target 2026
Solar + storage project J3981, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Battery storage project J3550, Dubois County
Battery storage
200 MWIn study Dubois, INMISO Apr 2024target 2027
Battery storage project J3948, Posey County
Battery storage
200 MWIn study Posey, INMISO Mar 2025target 2030
Moss Creek Solar
Solar
200 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Battery storage project J3357, Kosciusko County
Battery storage
200 MWIn study Kosciusko, INMISO Apr 2024target 2028
Battery storage project J2586, Clark County
Battery storage
200 MWIn study Clark, INMISO Sep 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)