United States › Grid › Interconnection queues › Indiana
BATTERY STORAGE · MISOBattery storage project J3357, Kosciusko County
Battery storage project J3357, Kosciusko County is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Kosciusko County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3357
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN INDIANA PUBLIC SERVICE COMPANY
- Connection point (POI)
- LEESBURG
- Location
- Kosciusko County, Indiana
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 15 April 2024
- Proposed online date
- December 2028
Location
Marker shows the centre of Kosciusko County; the queue data does not give exact sites.
Other requests in Kosciusko County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem