United States › Grid › Interconnection queues › Indiana
SOLAR + STORAGE · MISOSolar + storage project J3077, Gibson County
Solar + storage project J3077, Gibson County is a 250 MW solar + storage request in interconnection study in the MISO interconnection queue, in Gibson County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3077
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
- Connection point (POI)
- Francisco 345/138kV
- Location
- Gibson County, Indiana
- Technology
- Solar: 250 MW · Battery
- Total requested
- 250 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- November 2026
Location
Marker shows the centre of Gibson County; the queue data does not give exact sites.
Other requests in Gibson County
- Solar project J1388, Gibson CountySolar · 150 MW · agreement signed
- Battery storage project J3834, Gibson CountyBattery storage · 300 MW · in study
- Battery storage project J3873, Gibson CountyBattery storage · 200 MW · in study
- Solar + storage project J3733, Gibson CountySolar + storage · 150 MW · in study
- Solar + storage project J3983, Gibson CountySolar + storage · 100 MW · in study
- Solar project J1295, Gibson CountySolar · 280 MW · built
- Onshore wind project J842, Gibson CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J843, Gibson CountyOnshore wind · 200 MW · withdrawn
- Solar project J1296, Gibson CountySolar · 200 MW · withdrawn
- Solar project J1074, Gibson CountySolar · 200 MW · withdrawn
- Gas project G940, Gibson CountyGas · 105 MW · withdrawn
- Solar project J1950, Gibson CountySolar · 83.2 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem