United States › Grid › Interconnection queues › Indiana
SOLAR · MISOSolar project J1295, Gibson County
Solar project J1295, Gibson County is a 280 MW solar request built and operating in the MISO interconnection queue, in Gibson County, Indiana, connecting to DUKE ENERGY INDIANA.
Request details
- Queue ID
- J1295
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Gibson - Francisco 345kV Line
- Location
- Gibson County, Indiana
- Technology
- Solar: 280 MW
- Total requested
- 280 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 29 April 2019
- Agreement signed
- 7 October 2025
- Proposed online date
- December 2023
- Came online
- December 2023
Location
Marker shows the centre of Gibson County; the queue data does not give exact sites.
Other requests in Gibson County
- Solar project J1388, Gibson CountySolar · 150 MW · agreement signed
- Battery storage project J3834, Gibson CountyBattery storage · 300 MW · in study
- Solar + storage project J3077, Gibson CountySolar + storage · 250 MW · in study
- Battery storage project J3873, Gibson CountyBattery storage · 200 MW · in study
- Solar + storage project J3733, Gibson CountySolar + storage · 150 MW · in study
- Solar + storage project J3983, Gibson CountySolar + storage · 100 MW · in study
- Onshore wind project J842, Gibson CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J843, Gibson CountyOnshore wind · 200 MW · withdrawn
- Solar project J1296, Gibson CountySolar · 200 MW · withdrawn
- Solar project J1074, Gibson CountySolar · 200 MW · withdrawn
- Gas project G940, Gibson CountyGas · 105 MW · withdrawn
- Solar project J1950, Gibson CountySolar · 83.2 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem