United States βΊ Grid βΊ Interconnection queues βΊ Indiana
ONSHORE WIND Β· MISOOnshore wind project J843, Gibson County
Onshore wind project J843, Gibson County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Gibson County, Indiana, connecting to Duke Energy Corporation.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedFeb 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J843
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Duke Energy Corporation
- Connection point (POI)
- Gibson - Francisco 345kV Line
- Location
- Gibson County, Indiana
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Proposed online date
- September 2021
- Withdrawn
- February 2020
Location
Marker shows the centre of Gibson County; the queue data does not give exact sites.
Other requests in Gibson County
- Solar project J1388, Gibson CountySolar Β· 150 MW Β· agreement signed
- Battery storage project J3834, Gibson CountyBattery storage Β· 300 MW Β· in study
- Solar + storage project J3077, Gibson CountySolar + storage Β· 250 MW Β· in study
- Battery storage project J3873, Gibson CountyBattery storage Β· 200 MW Β· in study
- Solar + storage project J3733, Gibson CountySolar + storage Β· 150 MW Β· in study
- Solar + storage project J3983, Gibson CountySolar + storage Β· 100 MW Β· in study
- Solar project J1295, Gibson CountySolar Β· 280 MW Β· built
- Onshore wind project J842, Gibson CountyOnshore wind Β· 200 MW Β· withdrawn
- Solar project J1296, Gibson CountySolar Β· 200 MW Β· withdrawn
- Solar project J1074, Gibson CountySolar Β· 200 MW Β· withdrawn
- Gas project G940, Gibson CountyGas Β· 105 MW Β· withdrawn
- Solar project J1950, Gibson CountySolar Β· 83.2 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem