United States › Grid › Interconnection queues › Illinois

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Illinois — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown42374.6 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

423 requests · page 2 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J3525, Rock Island County
Battery storage
300 MWIn study Rock Island, ILMISO Apr 2024target 2028
Onshore wind project J3853, Iroquois County
Onshore wind
300 MWIn study Iroquois, ILMISO Dec 2024target 2029
Burr Oak Solar
Solar · Leeward Renewable Energy Development, LLC
300 MWIn study Dekalb, ILPJM Aug 2020target 2023
South Dixon Solar
Solar · Deriva Energy Solar, LLC
300 MWIn study Lee, ILPJM Mar 2020target 2022
Onshore wind project J4112, Rock Island County
Onshore wind
300 MWIn study Rock Island, ILMISO Oct 2025target 2030
Solar project AG2-363, Tazewell County
Solar · Mackinaw Solar LLC
300 MWIn study Tazewell, ILPJM Mar 2025target 2024
Wind + storage project J3027, Stark County
Wind + storage
300 MWIn study Stark, ILMISO Sep 2022target 2027
Battery storage project J3216, Peoria County
Battery storage
300 MWIn study Peoria, ILMISO Sep 2022target 2027
Battery storage project J3417, Macon County
Battery storage
300 MWIn study Macon, ILMISO Apr 2024target 2028
Black Diamond Solar
Solar · Black Diamond Solar Power, LLC
299 MWIn study Christian, ILPJM Mar 2019target 2022
Solar project J3012, Coles County
Solar
287 MWIn study Coles, ILMISO Sep 2022target 2026
Solar project AG2-453, Kendall County
Solar · Fox Valley Energy Facility, LLC
280 MWIn study Kendall, ILPJM Feb 2025target 2024
Solar project AH2-342, Stark County
Solar
280 MWIn study Stark, ILPJM Mar 2022target 2027
Solar project J813, Clay County
Solar
275 MWUnder construction Clay, ILMISO Jun 20172024
Solar project J2565, Iroquois County
Solar
265 MWIn study Iroquois, ILMISO Sep 2022target 2026
Beacon Solar
Solar · Beacon Solar, LLC
260 MWIn study Rock Island, ILPJM Sep 2020target 2023
Battery storage project AJ1-014, Will County
Battery storage
260 MWIn study Will, ILPJM May 2023target 2027
Livingston Wind
Onshore wind · Livingston Wind Project, LLC
255 MWIn study Livingston, ILPJM Sep 2018target 2021
Gipper Solar Farm
Solar · Gipper Solar Farm, LLC
255 MWIn study Whiteside, ILPJM Oct 2020target 2023
Onshore wind project J3078, Peoria County
Onshore wind
252 MWIn study Peoria, ILMISO Sep 2022target 2026
Onshore wind project J848, Christian County
Onshore wind
250 MWUnder construction Christian, ILMISO Jun 2017target 2021
Battery storage project J3883, Crawford County
Battery storage
250 MWIn study Crawford, ILMISO Feb 2025target 2030
Battery storage project J4198, Christian County
Battery storage
250 MWIn study Christian, ILMISO Sep 2025target 2030
Battery storage project AI1-149, Mchenry County
Battery storage
250 MWIn study Mchenry, ILPJM Sep 2022target 2025
Solar project J2793, Saline County
Solar
250 MWIn study Saline, ILMISO Sep 2022target 2026
Solar project J815, Christian County
Solar
250 MWUnder construction Christian, ILMISO Jun 2017target 2022
Solar project J1216, Washington County
Solar
250 MWAgreement signed Washington, ILMISO Apr 2019target 2026
Solar project J2973, Christian County
Solar
250 MWIn study Christian, ILMISO Sep 2022target 2026
Battery storage project AJ1-013, Will County
Battery storage
250 MWIn study Will, ILPJM May 2023target 2027
Solar project J3074, Randolph County
Solar
250 MWIn study Randolph, ILMISO Sep 2022target 2025
Solar + storage project J2267, Williamson County
Solar + storage
250 MWIn study Williamson, ILMISO Mar 2022target 2025
Solar + storage project AI1-172, Grundy County
Solar + storage
250 MWIn study Grundy, ILPJM Sep 2022target 2028
Solar project J3805, Fayette County
Solar
250 MWIn study Fayette, ILMISO Mar 2024target 2027
Solar project J2922, Jasper County
Solar
250 MWIn study Jasper, ILMISO Sep 2022target 2028
Onshore wind project J3750, Mercer County
Onshore wind
250 MWIn study Mercer, ILMISO Apr 2024target 2028
Onshore wind project J2275, Peoria County
Onshore wind
250 MWIn study Peoria, ILMISO Mar 2022target 2025
Solar project J3954, Christian County
Solar
250 MWIn study Christian, ILMISO Apr 2025target 2030
Solar project J3556, Montgomery County
Solar
250 MWIn study Montgomery, ILMISO Apr 2024target 2028
Onshore wind project J4018, Ford County
Onshore wind
250 MWIn study Ford, ILMISO May 2025target 2029
Solar project J1840, Dewitt County
Solar
250 MWIn study Dewitt, ILMISO Jun 2020target 2023
Battery storage project J4118, Mclean County
Battery storage
250 MWIn study Mclean, ILMISO Sep 2025target 2030
Solar project J800, White County
Solar
250 MWUnder construction White, ILMISO Jun 20172024
Solar project J2662, Cumberland County
Solar
250 MWIn study Cumberland, ILMISO Sep 2022target 2026
Solar project J3882, Crawford County
Solar
250 MWIn study Crawford, ILMISO Feb 2025target 2030
Solar + storage project AH2-113, Livingston County
Solar + storage
250 MWIn study Livingston, ILPJM Feb 2022target 2026
Solar project J4031, Scott County
Solar
245 MWIn study Scott, ILMISO May 2025target 2030
Solar project J3949, Scott County
Solar
245 MWIn study Scott, ILMISO Apr 2025target 2030
Onshore wind project J3856, Wabash County
Onshore wind
235 MWIn study Wabash, ILMISO Dec 2024target 2030
Battery storage project AI1-154, Will County
Battery storage
230 MWIn study Will, ILPJM Sep 2022target 2027
Battery storage project AH2-421, Grundy County
Battery storage
230 MWIn study Grundy, ILPJM Mar 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)