BATTERY STORAGE · PJMBattery storage project AJ1-014, Will County
Battery storage project AJ1-014, Will County is a 260 MW battery storage request in interconnection study in the PJM interconnection queue, in Will County, Illinois, connecting to ComEd.
Queue statusIn planning
- PlanningQueued May 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AJ1-014
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Will County Unit 4 CIR Transfer
- Location
- Will County, Illinois
- Technology
- Battery: 260 MW
- Total requested
- 260 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 24 May 2023
- Proposed online date
- June 2027
Location
Marker shows the centre of Will County; the queue data does not give exact sites.
Other requests in Will County
- Jackson GenerationGas · 120 MW · agreement signed
- Wilmington Solar Energy ProjectSolar + storage · 19.9 MW · agreement signed
- Battery storage project AJ1-013, Will CountyBattery storage · 250 MW · in study
- Battery storage project AI1-154, Will CountyBattery storage · 230 MW · in study
- Nuclear project AH1-698, Will CountyNuclear · 130 MW · in study
- Battery storage project AH1-165, Will CountyBattery storage · 72.0 MW · in study
- Solar + storage project AH2-199, Will CountySolar + storage · 51.7 MW · in study
- Gas project AH1-567, Will CountyGas · 5.0 MW · in study
- Aurora Battery StorageBattery storage · 10.0 MW · suspended
- Jackson GenerationGas · 1,201 MW · built
- Joliet Units 7 and 8Gas · 64.0 MW · built
- University Park North Energy CenterGas · 54.0 MW · built