🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Illinois

ONSHORE WIND · MISO

Onshore wind project J4018, Ford County

Onshore wind project J4018, Ford County is a 250 MW onshore wind request in interconnection study in the MISO interconnection queue, in Ford County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusIn planning
  1. PlanningQueued May 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J4018
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Other_
Location
Ford County, Illinois
Technology
Wind: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
2 May 2025
Proposed online date
June 2029

Location

Marker shows the centre of Ford County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Ford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem