ONSHORE WIND · MISOOnshore wind project G996, Ford County
Onshore wind project G996, Ford County is a 150 MW onshore wind request built and operating in the MISO interconnection queue, in Ford County, Illinois.
Request details
- Queue ID
- G996
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Paxton East 138kV Substation
- Location
- Ford County, Illinois
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- Optional
- Queue status
- Operational
- Entered queue
- 4 April 2008
- Agreement signed
- 5 February 2010
- Proposed online date
- December 2010
- Came online
- December 2010
Location
Marker shows the centre of Ford County; the queue data does not give exact sites.
Other requests in Ford County
- Solar project J3412, Ford CountySolar · 300 MW · in study
- Onshore wind project J4018, Ford CountyOnshore wind · 250 MW · in study
- Solar project J3095, Ford CountySolar · 200 MW · in study
- Surplus; J33/J734Other · 135 MW · in study
- Onshore wind project J845, Ford CountyOnshore wind · 120 MW · built
- Gas project J339, Ford CountyGas · 96.0 MW · built
- Gas project J734, Ford CountyGas · 57.1 MW · built
- Onshore wind project W1-030, Ford CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project W1-031, Ford CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project U4-010, Ford CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J108, Ford CountyOnshore wind · 165 MW · withdrawn
- Onshore wind project J375, Ford CountyOnshore wind · 124 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem