United States › Grid › Interconnection queues › Illinois
SOLAR · MISOSolar project J3095, Ford County
Solar project J3095, Ford County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Ford County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3095
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- 4PAXTON - 4J845POI 138.0kV
- Location
- Ford County, Illinois
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 13 September 2022
- Proposed online date
- September 2025
Location
Marker shows the centre of Ford County; the queue data does not give exact sites.
Other requests in Ford County
- Solar project J3412, Ford CountySolar · 300 MW · in study
- Onshore wind project J4018, Ford CountyOnshore wind · 250 MW · in study
- Surplus; J33/J734Other · 135 MW · in study
- Onshore wind project G996, Ford CountyOnshore wind · 150 MW · built
- Onshore wind project J845, Ford CountyOnshore wind · 120 MW · built
- Gas project J339, Ford CountyGas · 96.0 MW · built
- Gas project J734, Ford CountyGas · 57.1 MW · built
- Onshore wind project W1-030, Ford CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project W1-031, Ford CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project U4-010, Ford CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J108, Ford CountyOnshore wind · 165 MW · withdrawn
- Onshore wind project J375, Ford CountyOnshore wind · 124 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem