πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

ONSHORE WIND Β· MISO

Onshore wind project J108, Ford County

Onshore wind project J108, Ford County is a 165 MW onshore wind request withdrawn in the MISO interconnection queue, in Ford County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2009 (completed)
  2. Withdrawn / abandonedFeb 2012 (project stopped here)
  3. ConsentedFeb 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J108
Grid region
MISO (Midcontinent)
Connection point (POI)
Paxton East 138kV Substation
Location
Ford County, Illinois
Technology
Wind: 165 MW
Total requested
165 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
21 December 2009
Agreement signed
15 February 2012
Proposed online date
May 2010
Withdrawn
February 2012

Location

Marker shows the centre of Ford County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Ford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem