GAS · MISOGas project J734, Ford County
Gas project J734, Ford County is a 57.1 MW gas request built and operating in the MISO interconnection queue, in Ford County, Illinois, connecting to AMEREN ILLINOIS.
Request details
- Queue ID
- J734
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Gibson City South Substation
- Location
- Ford County, Illinois
- Technology
- Gas: 57.1 MW
- Total requested
- 57.1 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 10 November 2016
- Agreement signed
- 19 February 2019
- Proposed online date
- September 2017
- Came online
- September 2017
Location
Marker shows the centre of Ford County; the queue data does not give exact sites.
Other requests in Ford County
- Solar project J3412, Ford CountySolar · 300 MW · in study
- Onshore wind project J4018, Ford CountyOnshore wind · 250 MW · in study
- Solar project J3095, Ford CountySolar · 200 MW · in study
- Surplus; J33/J734Other · 135 MW · in study
- Onshore wind project G996, Ford CountyOnshore wind · 150 MW · built
- Onshore wind project J845, Ford CountyOnshore wind · 120 MW · built
- Gas project J339, Ford CountyGas · 96.0 MW · built
- Onshore wind project W1-030, Ford CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project W1-031, Ford CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project U4-010, Ford CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J108, Ford CountyOnshore wind · 165 MW · withdrawn
- Onshore wind project J375, Ford CountyOnshore wind · 124 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem