United States βΊ Grid βΊ Interconnection queues βΊ Illinois
ONSHORE WIND Β· MISOOnshore wind project J375, Ford County
Onshore wind project J375, Ford County is a 124 MW onshore wind request withdrawn in the MISO interconnection queue, in Ford County, Illinois.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2014 (completed)
- Withdrawn / abandonedOct 2016 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J375
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Gibson City South Substation 138 kV
- Location
- Ford County, Illinois
- Technology
- Wind: 124 MW
- Total requested
- 124 MW
- Study phase
- Network Upgrade
- Queue status
- Withdrawn
- Entered queue
- 7 July 2014
- Proposed online date
- September 2015
- Withdrawn
- October 2016
Location
Marker shows the centre of Ford County; the queue data does not give exact sites.
Other requests in Ford County
- Solar project J3412, Ford CountySolar Β· 300 MW Β· in study
- Onshore wind project J4018, Ford CountyOnshore wind Β· 250 MW Β· in study
- Solar project J3095, Ford CountySolar Β· 200 MW Β· in study
- Surplus; J33/J734Other Β· 135 MW Β· in study
- Onshore wind project G996, Ford CountyOnshore wind Β· 150 MW Β· built
- Onshore wind project J845, Ford CountyOnshore wind Β· 120 MW Β· built
- Gas project J339, Ford CountyGas Β· 96.0 MW Β· built
- Gas project J734, Ford CountyGas Β· 57.1 MW Β· built
- Onshore wind project W1-030, Ford CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project W1-031, Ford CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project U4-010, Ford CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J108, Ford CountyOnshore wind Β· 165 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem