Solar project J1216, Washington County

Solar project J1216, Washington County is a 250 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Washington County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedDec 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1216
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Ashley 138 kV Substation
Location
Washington County, Illinois
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
27 April 2019
Agreement signed
10 December 2024
Proposed online date
June 2026

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem