United States βΊ Grid βΊ Interconnection queues βΊ Illinois
SOLAR Β· MISOSolar project J1225, Washington County
Solar project J1225, Washington County is a 160 MW solar request withdrawn in the MISO interconnection queue, in Washington County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedAug 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1225
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Ashley-Turkey Hill Line 1482, between the Okawville and North Nashville substations
- Location
- Washington County, Illinois
- Technology
- Solar: 160 MW
- Total requested
- 160 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 27 April 2019
- Proposed online date
- September 2023
- Withdrawn
- August 2021
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Solar project J1094, Washington CountySolar Β· 150 MW Β· under construction
- Solar project J1216, Washington CountySolar Β· 250 MW Β· agreement signed
- Wind + storage project J2690, Washington CountyWind + storage Β· 500 MW Β· in study
- Battery storage project J3316, Washington CountyBattery storage Β· 150 MW Β· in study
- Coal project IP14, Washington CountyCoal Β· 1,500 MW Β· built
- Coal project G495, Washington CountyCoal Β· 150 MW Β· built
- Other project IP11, Washington CountyOther Β· 500 MW Β· withdrawn
- Battery storage project J2422, Washington CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project J2463, Washington CountySolar Β· 200 MW Β· withdrawn
- Solar project J1301, Washington CountySolar Β· 150 MW Β· withdrawn
- Solar project J3410, Washington CountySolar Β· 120 MW Β· withdrawn
- Solar + storage project J3013, Washington CountySolar + storage Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem