Withdrawn queue requests in ERCOT (Texas) — page 15

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,158262.0 GW
Active in queue447.3 GW1,986 requests
Agreement signed119.3 GW578 requests
Withdrawn1,158262.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,158 requests · page 15 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
El Zorro Storage
Other · Cypress Creek Renewables
127 MWWithdrawn / abandoned Webb, TXERCOT Jun 2018target 2021
Atascosa I Solar
Solar · Core Solar
127 MWWithdrawn / abandoned Dawson, TXERCOT Jun 2018target 2022
Century Oak Wind
Onshore wind · Engie
126 MWWithdrawn / abandoned Callahan, TXERCOT Jan 2018target 2023
Highwire Storage
Battery storage · Cypress Creek Renewables
126 MWWithdrawn / abandoned ERCOT Mar 2018target 2020
Palacios BESS
Battery storage · BRP BLUE TOPAZ 11, LLC
126 MWWithdrawn / abandoned Cameron, TXERCOT May 2023target 2027
Roscoe 2
Onshore wind · Airtricity, Inc
125 MWWithdrawn / abandoned ERCOT Jul 2006
Magnet Wind
Onshore wind · Lane City Wind, LLC
125 MWWithdrawn / abandoned Wharton, TXERCOT Apr 2018target 2021
Bosque Upgrade
Gas · Calpine
124 MWWithdrawn / abandoned ERCOT Feb 2014target 2019
TXP Reeves G
Gas · TXP Holdings
123 MWWithdrawn / abandoned ERCOT Oct 2013target 2018
TXP Winkler G
Gas · TXP Holdings
123 MWWithdrawn / abandoned ERCOT Nov 2013target 2018
Flamingo Solar
Solar · ABEI ENERGY&INFRASTRUCTURE LLC
123 MWWithdrawn / abandoned Tom Green, TXERCOT Mar 2019target 2022
Raven Solar
Solar · Raven Solar, LLC
123 MWWithdrawn / abandoned Wharton, TXERCOT Jan 2022target 2025
Hale Community W 2
Onshore wind · Nextera
122 MWWithdrawn / abandoned ERCOT Nov 2013target 2020
Desert Vine Solar
Solar · Desert Vine Solar LLC
121 MWWithdrawn / abandoned ERCOT May 2020target 2026
Racetrack Solar
Solar · Innergex Renewables USA, LLC
121 MWWithdrawn / abandoned Uvalde, TXERCOT Nov 2019target 2026
Normangee Solar
Solar · Normangee Solar LLC
121 MWWithdrawn / abandoned ERCOT Mar 2023target 2027
Dos Rios Energy Storage GIM
Other · DOS RIOS SOLAR, LLC
121 MWWithdrawn / abandoned Milam, TXERCOT target 2025
EK Tipton Solar
Solar · EnergieKontor US Texas SP 1 LLC
120 MWWithdrawn / abandoned Reeves, TXERCOT Sep 2018target 2023
Murphy Lake Solar
Solar · S Power
120 MWWithdrawn / abandoned Kaufman, TXERCOT Feb 2017target 2021
Childress County Wind
Onshore wind · CHILDRESS COUNTY WIND 1, LLC
120 MWWithdrawn / abandoned ERCOT Oct 2006target 2014
SP-TX-08
Solar · Solar Prime
120 MWWithdrawn / abandoned ERCOT Jun 2014target 2016
Reiher Solar
Solar · EnergieKontor US Texas SP 7 LLC
120 MWWithdrawn / abandoned Upton, TXERCOT Jan 2018target 2023
Wild Horse Mountain
Onshore wind · Iberdrola
120 MWWithdrawn / abandoned ERCOT Mar 2005target 2050
Pflugerville 2 Solar
Solar · RRE Power LLC 1
120 MWWithdrawn / abandoned Travis, TXERCOT Mar 2018target 2025
TX04a Farm
Onshore wind · Gamesa energia
120 MWWithdrawn / abandoned ERCOT Dec 2004target 2050
Sterling Prairie Solar
Solar · RWE Solar Development, LLC
120 MWWithdrawn / abandoned ERCOT Apr 2019target 2025
Crios BESS Placeholder
Battery storage · BRP Crios BESS LLC
118 MWWithdrawn / abandoned ERCOT target 2028
Barrel Summit Storage
Other · KCE TX 14, LLC
117 MWWithdrawn / abandoned Ellis, TXERCOT Jun 2020target 2022
Friendswood II
Gas · Friendswood Energy 2
117 MWWithdrawn / abandoned Brazoria, TXERCOT May 2018target 2021
Adamstown Storage
Other · Adams Creek Solar Project, LLC
117 MWWithdrawn / abandoned Wichita, TXERCOT Nov 2018target 2025
Southern Star Solar SLF
Solar · Southern Star Solar Project, LLC
116 MWWithdrawn / abandoned ERCOT Mar 2025target 2029
Holly Branch Storage
Battery storage · Holly Branch Solar, LLC
115 MWWithdrawn / abandoned ERCOT Jun 2023target 2027
Redfish W 2b
Onshore wind · Eon
115 MWWithdrawn / abandoned ERCOT Jan 2013target 2016
Sun Valley 2
Solar · Sun Valley Solar LLC
115 MWWithdrawn / abandoned Hill, TXERCOT Mar 2019target 2021
Savanna Prairie Storage
Battery storage · Savanna Prairie Storage, LLC
114 MWWithdrawn / abandoned ERCOT Oct 2024target 2028
Blue Summit W 2
Onshore wind · Nextera
114 MWWithdrawn / abandoned ERCOT Feb 2013target 2018
Keechi Creek Wind Farm
Onshore wind · Texas Land Partners
113 MWWithdrawn / abandoned ERCOT Jun 2007target 2050
Rustler Solar
Solar · Cypress Creek Renewables
113 MWWithdrawn / abandoned ERCOT Sep 2017target 2020
SSE phase 1
Onshore wind · Spinning Star Energy LLC
113 MWWithdrawn / abandoned ERCOT Jul 2011target 2050
SSE phase 1
Onshore wind · Spinning Star Energy LLC
112 MWWithdrawn / abandoned ERCOT Dec 2012target 2013
Green Valley Gas
Gas · Denton Municipal Electric
112 MWWithdrawn / abandoned ERCOT Nov 2015target 2017
Long Draw Energy Project
Onshore wind · Turner/Ross Wind Development LLC
112 MWWithdrawn / abandoned ERCOT May 2010target 2015
Pequin BESS Alt#1
Other · Pequin Energy Storage, LLC
111 MWWithdrawn / abandoned Brazoria, TXERCOT Jan 2021target 2023
Miami Wind G3
Onshore wind · Invenergy
111 MWWithdrawn / abandoned ERCOT Jun 2011target 2016
Galloway 2 Storage
Other · 224WB 8ME LLC
110 MWWithdrawn / abandoned Concho, TXERCOT Aug 2019target 2021
West Texas Solar 1
Solar · West Texas Solar LLC
110 MWWithdrawn / abandoned ERCOT Dec 2013target 2015
FAS1 Solar
Solar · Macquarie Cap
110 MWWithdrawn / abandoned ERCOT Dec 2013target 2018
Morgan Ranch Wind Park
Onshore wind · Wind Plus (Morgan Ranch Wind Park LLC)
108 MWWithdrawn / abandoned ERCOT Jun 2003target 2050
Clapton BESS
Battery storage · Clapton Storage
106 MWWithdrawn / abandoned ERCOT target 2027
Sepanta Wind Project
Onshore wind · Sepanta Wind Energy, LLC
106 MWWithdrawn / abandoned ERCOT Mar 2010target 2014
Page 15 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)