United States βΊ Grid βΊ Interconnection queues βΊ Texas
GAS Β· ERCOTFriendswood II
Friendswood II is a 117 MW gas request withdrawn in the ERCOT interconnection queue, in Brazoria County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2018 (completed)
- Withdrawn / abandonedSep 2020 (project stopped here)
- ConsentedSep 2019 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 19INR0180
- Grid region
- ERCOT (Texas)
- Developer
- Friendswood Energy 2
- Connection point (POI)
- 47170 HOC 138kV
- Location
- Brazoria County, Texas
- Technology
- Gas: 117 MW
- Total requested
- 117 MW
- Study phase
- IA
- Queue status
- Withdrawn
- Entered queue
- 16 May 2018
- Agreement signed
- 9 September 2019
- Proposed online date
- February 2021
- Withdrawn
- September 2020
Location
Marker shows the centre of Brazoria County; the queue data does not give exact sites.
Other requests in Brazoria County
- Austin Bayou SolarSolar + storage Β· 503 MW Β· agreement signed
- Gamay Energy StorageBattery storage Β· 419 MW Β· agreement signed
- Aldrin 345 BESSBattery storage Β· 362 MW Β· agreement signed
- Cottonwood Bayou SolarSolar Β· 351 MW Β· agreement signed
- Myrtle SolarSolar Β· 321 MW Β· agreement signed
- Elio BESSBattery storage Β· 317 MW Β· agreement signed
- First Capitol BESSBattery storage Β· 258 MW Β· agreement signed
- Hastings Park BESSBattery storage Β· 256 MW Β· agreement signed
- Clutch City Solar Phase IISolar Β· 251 MW Β· agreement signed
- Tanglewood SolarSolar Β· 251 MW Β· agreement signed
- Aldrin 138 BESSBattery storage Β· 207 MW Β· agreement signed
- Desna BESSBattery storage Β· 206 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem