GAS Β· ERCOT

TXP Winkler G

TXP Winkler G is a 123 MW gas request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
15INR0053
Grid region
ERCOT (Texas)
Developer
TXP Holdings
Connection point (POI)
tap 138kV 1074 Wink - 1009 Yucca Dr near Wink
Technology
Gas: 123 MW
Total requested
123 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
1 November 2013
Proposed online date
December 2018

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem