ONSHORE WIND Β· ERCOTRedfish W 2b
Redfish W 2b is a 115 MW onshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2013 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedAug 2015 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 14INR0041b
- Grid region
- ERCOT (Texas)
- Developer
- Eon
- Connection point (POI)
- Perm = tap 8383 NEdinb - 8318 RHondo 345kV, ~10.5 mi to RHondo new sub Bonilla +18 mi gen tie. Temp = tap Ajo-RHondo 345kV, ~13.5 mi to RHondo
- Technology
- Wind: 115 MW
- Total requested
- 115 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 2 January 2013
- Agreement signed
- 12 August 2015
- Proposed online date
- December 2016
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem