BATTERY STORAGE Β· ERCOT

Crios BESS Placeholder

Crios BESS Placeholder is a 118 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
28INR0379
Grid region
ERCOT (Texas)
Developer
BRP Crios BESS LLC
Connection point (POI)
Tap 138 kV 1649 HASSE_P8 - 1684 SABANA_8
Technology
Battery: 118 MW
Total requested
118 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Proposed online date
March 2028

Location

No county location in the queue data.

Power plants in Β· Transmission lines in