Palacios BESS

Palacios BESS is a 126 MW battery storage request withdrawn in the ERCOT interconnection queue, in Cameron County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandonedApr 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0418
Grid region
ERCOT (Texas)
Developer
BRP BLUE TOPAZ 11, LLC
Connection point (POI)
5767 HIWAY511SUB8 138kV
Location
Cameron County, Texas
Technology
Battery: 126 MW
Total requested
126 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
14 May 2023
Proposed online date
November 2027
Withdrawn
April 2025

Location

Marker shows the centre of Cameron County; the queue data does not give exact sites.