FAS1 Solar

FAS1 Solar is a 110 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
15INR0069
Grid region
ERCOT (Texas)
Developer
Macquarie Cap
Connection point (POI)
(#6655) to (#6630)
Technology
Solar: 110 MW
Total requested
110 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
23 December 2013
Proposed online date
November 2018

Location

No county location in the queue data.

Power plants in Β· Transmission lines in