ONSHORE WIND Β· ERCOT

Blue Summit W 2

Blue Summit W 2 is a 114 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
14INR0048_1
Grid region
ERCOT (Texas)
Developer
Nextera
Connection point (POI)
140383 Blue 345kV
Technology
Wind: 114 MW
Total requested
114 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
26 February 2013
Proposed online date
November 2018

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem