Murphy Lake Solar

Murphy Lake Solar is a 120 MW solar request withdrawn in the ERCOT interconnection queue, in Kaufman County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2017 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. ConsentedDec 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
19INR0033
Grid region
ERCOT (Texas)
Developer
S Power
Connection point (POI)
6904 CombinRC 138kV
Location
Kaufman County, Texas
Technology
Solar: 120 MW
Total requested
120 MW
Study phase
IA
Queue status
Withdrawn
Entered queue
5 February 2017
Agreement signed
27 December 2019
Proposed online date
March 2021
Withdrawn
March 2020

Location

Marker shows the centre of Kaufman County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Kaufman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem