Rustler Solar

Rustler Solar is a 113 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2017 (completed)
  2. Withdrawn / abandonedAug 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0030
Grid region
ERCOT (Texas)
Developer
Cypress Creek Renewables
Connection point (POI)
tap 138kV 5827 Moore - 5895 Pearsall
Technology
Solar: 113 MW
Total requested
113 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
21 September 2017
Proposed online date
June 2020
Withdrawn
August 2018

Location

No county location in the queue data.

Power plants in Β· Transmission lines in