United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTRacetrack Solar
Racetrack Solar is a 121 MW solar request withdrawn in the ERCOT interconnection queue, in Uvalde County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2019 (completed)
- Withdrawn / abandonedApr 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21INR0454
- Grid region
- ERCOT (Texas)
- Developer
- Innergex Renewables USA, LLC
- Connection point (POI)
- tap 138kV 8234 Uvalde - 8236 West Batesville
- Location
- Uvalde County, Texas
- Technology
- Solar: 121 MW
- Total requested
- 121 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 17 November 2019
- Proposed online date
- December 2026
- Withdrawn
- April 2024
Location
Marker shows the centre of Uvalde County; the queue data does not give exact sites.
Other requests in Uvalde County
- Nightfall SolarSolar Β· 181 MW Β· agreement signed
- Photo Solar 2Solar + storage Β· 300 MW Β· in study
- Photo BESS 2Solar + storage Β· 150 MW Β· in study
- Photo Solar 1Solar + storage Β· 150 MW Β· in study
- Photo BESS 3Solar + storage Β· 100 MW Β· in study
- Sunsetter BESSBattery storage Β· 100 MW Β· in study
- Photo BESS 1Solar + storage Β· 75.0 MW Β· in study
- Ashra Solar SLFSolar + storage Β· 40.3 MW Β· in study
- Ashra Storage SLFSolar + storage Β· 1.6 MW Β· in study
- Fluorite SolarSolar Β· 25.0 MW Β· suspended
- Basalt SolarSolar Β· 20.0 MW Β· suspended
- SunRaySolar Β· 204 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem