SOLAR Β· ERCOT

Racetrack Solar

Racetrack Solar is a 121 MW solar request withdrawn in the ERCOT interconnection queue, in Uvalde County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2019 (completed)
  2. Withdrawn / abandonedApr 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0454
Grid region
ERCOT (Texas)
Developer
Innergex Renewables USA, LLC
Connection point (POI)
tap 138kV 8234 Uvalde - 8236 West Batesville
Location
Uvalde County, Texas
Technology
Solar: 121 MW
Total requested
121 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
17 November 2019
Proposed online date
December 2026
Withdrawn
April 2024

Location

Marker shows the centre of Uvalde County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Uvalde County