πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Pflugerville 2 Solar

Pflugerville 2 Solar is a 120 MW solar request withdrawn in the ERCOT interconnection queue, in Travis County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedAug 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0061
Grid region
ERCOT (Texas)
Developer
RRE Power LLC 1
Connection point (POI)
tap 138kV 7336 Gillie - 3650 Elgin
Location
Travis County, Texas
Technology
Solar: 120 MW
Total requested
120 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
4 March 2018
Proposed online date
June 2025
Withdrawn
August 2023

Location

Marker shows the centre of Travis County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Travis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem