SOLAR · ERCOT

Giga Austin Solar

Giga Austin Solar is a -53.3 MW solar request in interconnection study in the ERCOT interconnection queue, in Travis County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0372
Grid region
ERCOT (Texas)
Developer
GIGA TEXAS ENERGY LLC
Connection point (POI)
7047 HORNSBY Substation 138kV
Location
Travis County, Texas
Technology
Solar: -53.3 MW
Total requested
-53.3 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
18 July 2022
Proposed online date
March 2025

Location

Marker shows the centre of Travis County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Travis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem