BATTERY STORAGE Β· ERCOT

Clapton BESS

Clapton BESS is a 106 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
27INR0405
Grid region
ERCOT (Texas)
Developer
Clapton Storage
Connection point (POI)
345 kV Buckhorn Switch (#3424) to Brown Switch(#1444)
Technology
Battery: 106 MW
Total requested
106 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Proposed online date
August 2027

Location

No county location in the queue data.

Power plants in Β· Transmission lines in