OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas — page 10

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,094476.4 GW
Active in queue476.4 GW2,094 requests
Agreement signed124.6 GW606 requests
Withdrawn917184.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,094 requests · page 10 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Bendito Wind
Onshore wind · Bendito Wind Farm, LLC
300 MWIn study Webb, TXERCOT Jul 2025target 2029
Solar + storage project GEN-2024-050, Castro County
Solar + storage
300 MWIn study Castro, TXSPP Oct 2024target 2028
Photo Solar 2
Solar + storage · CED Development Inc.
300 MWIn study Uvalde, TXERCOT Sep 2022target 2027
Arroyo Del Bisonte Solar
Solar · Sunchase Power
300 MWPaused / redesign Wharton, TXERCOT May 2018target 2021
Pierce Wind
Onshore wind
300 MWPaused / redesign Wharton, TXERCOT Jan 2018
SP Jaguar BESS
Other · PP Jaguar BESS LLC
300 MWPaused / redesign Mclennan, TXERCOT Mar 20212025
Solar + storage project GEN-2024-336, Yoakum County
Solar + storage
300 MWIn study Yoakum, TXSPP Mar 2025target 2029
Battery storage project GEN-2024-SR15, Yoakum County
Battery storage
300 MWIn study Yoakum, TXSPP Oct 2024target 2026
Mandolin Solar SLF
Solar + storage · Mandolin Solar Project, LLC
300 MWIn study Starr, TXERCOT Jul 2024target 2029
Onshore wind project GEN-2017-151, Crosby County
Onshore wind
300 MWAgreement signed Crosby, TXSPP Nov 2017target 2026
Onshore wind project GEN-2018-099, Parmer County
Onshore wind
300 MWAgreement signed Parmer, TXSPP Nov 2018target 2027
Solar + storage project GEN-2024-364, Randall County
Solar + storage
300 MWIn study Randall, TXSPP Mar 2025target 2028
Solar project GEN-2024-317, Cottle County
Solar
300 MWIn study Cottle, TXSPP Mar 2025target 2030
Solar project GEN-2024-077, Hutchinson County
Solar
300 MWIn study Hutchinson, TXSPP Oct 2024target 2029
Selenite Springs Solar
Solar · Selenite Springs Solar, LLC
300 MWIn study Pecos, TXERCOT Apr 2025target 2028
Solar project GEN-2024-068, Morris County
Solar
300 MWIn study Morris, TXSPP Oct 2024target 2028
Diversion Wind
Onshore wind
300 MWPaused / redesign Baylor, TXERCOT Sep 2019target 2024
Onshore wind project GEN-2025-GR6, Dimmit County
Onshore wind
300 MWIn study Dimmit, TXSPP Nov 2025
Gardner Draw Solar
Solar · RWE Clean Energy Development, LLC
300 MWAgreement signed Glasscock, TXERCOT Oct 2024target 2027
Peach Creek Solar
Solar · Acciona Energy USA Global LLC
300 MWIn study Wharton, TXERCOT Dec 2024target 2028
Solar project J3045, Orange County
Solar
300 MWIn study Orange, TXMISO Sep 2022target 2026
Wisdom Solar SLF
Solar + storage · Wisdom Green Energy LLC
299 MWIn study Pecos, TXERCOT Feb 2025target 2027
Board Creek Wind
Onshore wind · Limestone Wind Project, LLC
299 MWAgreement signed Navarro, TXERCOT Apr 2019target 2026
Barranca Wind 2
Onshore wind · Barranca Wind Energy, LLC
299 MWIn study Jim Hogg, TXERCOT Jul 2025target 2028
Camino Ranch Storage SLF
Solar + storage · Camino Solar Ranch, LLC
298 MWIn study Houston, TXERCOT Oct 2022target 2028
Solar project GEN-2020-054, Bowie County
Solar
298 MWAgreement signed Bowie, TXSPP Apr 2020target 2027
Palo Verde Wind
Wind + storage · RWE Clean Energy Development, LLC
298 MWIn study San Patricio, TXERCOT Apr 2024target 2027
Aquilla Lake 3 Wind
Onshore wind · Aquilla Lake 3 Wind
297 MWAgreement signed Hill, TXERCOT Mar 2021target 2027
Prairie Hill Wind
Onshore wind · Prairie Hill LLC
297 MWAgreement signed Mclennan, TXERCOT Jun 20172020
Camino Ranch Solar SLF
Solar + storage · Camino Ranch Solar Project LLC
296 MWIn study Houston, TXERCOT Oct 2022target 2028
Fortuna Wind
Onshore wind · RWE Renewables Development, LLC
295 MWAgreement signed Jack, TXERCOT Mar 2020target 2026
Columbine Wind
Onshore wind · Wilson Wind LLC
295 MWIn study Gonzales, TXERCOT Feb 2025target 2029
Sanders Hollow Energy Center
Onshore wind · Sanders Hollow Energy Center, LLC
293 MWIn study Dickens, TXERCOT Oct 2024target 2028
Windjammer Windpower
Onshore wind · Windjammer Windpower, LLC
293 MWAgreement signed Glasscock, TXERCOT Sep 2024target 2028
Grapefruit Solar
Solar · Grapefruit Solar LLC
291 MWAgreement signed Hidalgo, TXERCOT Feb 2024target 2028
Vista Bluff Wind 2
Onshore wind
290 MWPaused / redesign Upton, TXERCOT Sep 2024
Vista Bluff Wind 1
Onshore wind
290 MWPaused / redesign Upton, TXERCOT Sep 2024
Vista Bluff Wind II "Alternate POI"
Onshore wind · Vista Bluff Windpower, LLC
290 MWIn study Upton, TXERCOT Sep 2025target 2029
Vista Bluff Wind I "Alternate POI"
Onshore wind · Vista Bluff Windpower, LLC
290 MWIn study Upton, TXERCOT Sep 2025target 2029
Tres Rios Ranch BESS
Solar + storage · LectricWind LLC
290 MWIn study Upton, TXERCOT May 2023target 2027
Shifting Gale Wind
Onshore wind
289 MWPaused / redesign Castro, TXERCOT Apr 2018target 2025
Onshore wind project J3902, Jefferson County
Onshore wind
289 MWIn study Jefferson, TXMISO Feb 2025target 2028
Sandow Solar
Solar · Sandow Lakes Ranch Solar I, LLC
287 MWIn study Milam, TXERCOT Sep 2020target 2028
Baker Branch BESS
Battery storage · Mockingbird Storage Center, LLC
287 MWIn study Lamar, TXERCOT Jun 2025target 2029
Inadale BESS
Solar + storage · Inadale BESS, LLC
287 MWIn study Scurry, TXERCOT Feb 2023target 2028
Spindletop Solar
Solar + storage · Banita Creek Solar LLC
286 MWAgreement signed Nacogdoches, TXERCOT Jul 2024target 2027
Fierce River BESS
Solar + storage · Rio Grande Solar LLC
285 MWIn study Starr, TXERCOT Mar 2024target 2029
Monarch Creek Wind
Onshore wind · MONARCH CREEK WIND, LLC
284 MWAgreement signed Throckmorton, TXERCOT Apr 2019target 2027
Fivemile Wind
Onshore wind · Longview Wind, LLC
282 MWIn study Dawson, TXERCOT Apr 2025target 2028
Impala Flats Wind
Onshore wind · Antelope Flats Wind, LLC
282 MWIn study Lynn, TXERCOT Jan 2019target 2026
Page 10 of 42

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)