United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Fortuna Wind

Fortuna Wind is a 295 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Jack County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2020 (completed)
  2. ConsentedAug 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0301
Grid region
ERCOT (Texas)
Developer
RWE Renewables Development, LLC
Connection point (POI)
Tap 345kV 1429 Jacksboro - 1730 WKrum
Location
Jack County, Texas
Technology
Wind: 295 MW
Total requested
295 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
6 March 2020
Agreement signed
8 August 2024
Proposed online date
July 2026

Location

Marker shows the centre of Jack County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jack County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem