Possum Kingdom Solar

Possum Kingdom Solar is a 262 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Jack County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0118
Grid region
ERCOT (Texas)
Developer
PK Solar, LLC
Connection point (POI)
Tap 345kV 1421 Willow Creek Switch – 11523 Thomas Price
Location
Jack County, Texas
Technology
Solar: 262 MW · Battery
Total requested
262 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
13 September 2021
Proposed online date
October 2027

Location

Marker shows the centre of Jack County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jack County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem