🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Campsey Wind

Campsey Wind is a 238 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Jack County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0174
Grid region
ERCOT (Texas)
Developer
RWE Clean Energy Development, LLC
Connection point (POI)
tap 345kV 1458 Cobb - 1429 Jacksboro
Location
Jack County, Texas
Technology
Wind: 238 MW
Total requested
238 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
9 February 2021
Proposed online date
June 2028

Location

Marker shows the centre of Jack County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jack County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem