United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· ERCOTDiversion Wind
Diversion Wind is a 300 MW onshore wind request suspended in the ERCOT interconnection queue, in Baylor County, Texas.
Queue statusPaused / redesign
- PlanningQueued Sep 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 21INR0432
- Grid region
- ERCOT (Texas)
- Location
- Baylor County, Texas
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Queue status
- Suspended
- Entered queue
- 9 September 2019
- Proposed online date
- December 2024
Location
Marker shows the centre of Baylor County; the queue data does not give exact sites.
Other requests in Baylor County
- Dundee East A WindOnshore wind Β· 524 MW Β· agreement signed
- Dundee East B WindOnshore wind Β· 261 MW Β· agreement signed
- Velveteen Solar ISolar Β· 509 MW Β· in study
- Velveteen Solar IISolar Β· 306 MW Β· in study
- Onshore wind project GEN-2017-033, Baylor CountyOnshore wind Β· 200 MW Β· built
- S_Hills WindOnshore wind Β· 30.2 MW Β· built
- Dundee East A Wind PlaceholderOnshore wind Β· 524 MW Β· withdrawn
- Onshore wind project GEN-2022-191, Baylor CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2018-122, Baylor CountyOnshore wind Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem