ONSHORE WIND · SPP

Onshore wind project GEN-2017-033, Baylor County

Onshore wind project GEN-2017-033, Baylor County is a 200 MW onshore wind request built and operating in the SPP interconnection queue, in Baylor County, Texas, connecting to AEP.

Queue statusOperating
  1. PlanningQueued May 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-033
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Oklaunion 345 kV sub
Location
Baylor County, Texas
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
31 May 2017
Proposed online date
December 2024
Came online
December 2024

Location

Marker shows the centre of Baylor County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Baylor County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem