ONSHORE WIND · SPPOnshore wind project GEN-2017-033, Baylor County
Onshore wind project GEN-2017-033, Baylor County is a 200 MW onshore wind request built and operating in the SPP interconnection queue, in Baylor County, Texas, connecting to AEP.
Request details
- Queue ID
- GEN-2017-033
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Oklaunion 345 kV sub
- Location
- Baylor County, Texas
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 31 May 2017
- Proposed online date
- December 2024
- Came online
- December 2024
Location
Marker shows the centre of Baylor County; the queue data does not give exact sites.
Other requests in Baylor County
- Dundee East A WindOnshore wind · 524 MW · agreement signed
- Dundee East B WindOnshore wind · 261 MW · agreement signed
- Velveteen Solar ISolar · 509 MW · in study
- Velveteen Solar IISolar · 306 MW · in study
- Diversion WindOnshore wind · 300 MW · suspended
- S_Hills WindOnshore wind · 30.2 MW · built
- Dundee East A Wind PlaceholderOnshore wind · 524 MW · withdrawn
- Onshore wind project GEN-2022-191, Baylor CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2018-122, Baylor CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem