United States › Grid › Interconnection queues › Texas

ONSHORE WIND · SPP

Onshore wind project GEN-2018-099, Parmer County

Onshore wind project GEN-2018-099, Parmer County is a 300 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Parmer County, Texas, connecting to SPS.

Queue statusConsented
  1. PlanningQueued Nov 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-099
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tolk 230kV Substation
Location
Parmer County, Texas
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
21 November 2018
Proposed online date
December 2027

Location

Marker shows the centre of Parmer County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Parmer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem