Solar + storage project GEN-2024-364, Randall County

Solar + storage project GEN-2024-364, Randall County is a 300 MW solar + storage request in interconnection study in the SPP interconnection queue, in Randall County, Texas, connecting to SPS.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-364
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Bushland 230 kV Substation
Location
Randall County, Texas
Technology
Solar: 300 MW · Battery
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
October 2028

Location

Marker shows the centre of Randall County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Randall County