πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2006-045, Randall County

Onshore wind project GEN-2006-045, Randall County is a 240 MW onshore wind request withdrawn in the SPP interconnection queue, in Randall County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2006-045
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tap Potter - Plant X 230kV (South Randle County) 230kV
Location
Randall County, Texas
Technology
Wind: 240 MW
Total requested
240 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
5 December 2006
Proposed online date
December 2008

Location

Marker shows the centre of Randall County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Randall County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem