Withdrawn queue requests in South Dakota, SPP

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown559,641 MW
Active in queue1,638 MW9 requests
Agreement signed669 MW3 requests
Withdrawn559,641 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

55 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2023-106, Hyde County
Onshore wind
504 MWWithdrawn / abandoned Hyde, SDSPP Oct 2023target 2028
Onshore wind project GEN-2017-114, Dewey County
Onshore wind
450 MWWithdrawn / abandoned Dewey, SDSPP Oct 2017target 2021
Solar project GEN-2022-174, Buffalo County
Solar
370 MWWithdrawn / abandoned Buffalo, SDSPP Feb 2023target 2026
Solar project GEN-2022-020, Walworth County
Solar
355 MWWithdrawn / abandoned Walworth, SDSPP Jun 20222025
Onshore wind project GEN-2017-200, Beadle County
Onshore wind
302 MWWithdrawn / abandoned Beadle, SDSPP Nov 2017target 2026
Onshore wind project GEN-2022-034, Union County
Onshore wind
300 MWWithdrawn / abandoned Union, SDSPP Jun 20222025
Onshore wind project GEN-2017-223, Haakon County
Onshore wind
250 MWWithdrawn / abandoned Haakon, SDSPP Nov 2017target 2020
Onshore wind project GEN-2017-020, Perkins County
Onshore wind
250 MWWithdrawn / abandoned Perkins, SDSPP May 2017target 2020
Onshore wind project GEN-2017-019, Haakon County
Onshore wind
250 MWWithdrawn / abandoned Haakon, SDSPP May 2017target 2019
Onshore wind project GEN-2022-068, Hyde County
Onshore wind
250 MWWithdrawn / abandoned Hyde, SDSPP Aug 2022target 2026
Onshore wind project GEN-2024-202, Hyde County
Onshore wind
250 MWWithdrawn / abandoned Hyde, SDSPP Mar 2025target 2030
Onshore wind project GEN-2022-069, Hyde County
Onshore wind
250 MWWithdrawn / abandoned Hyde, SDSPP Aug 2022target 2026
Onshore wind project GEN-2022-070, Hyde County
Onshore wind
250 MWWithdrawn / abandoned Hyde, SDSPP Aug 2022target 2026
Onshore wind project GEN-2023-105, Hyde County
Onshore wind
249 MWWithdrawn / abandoned Hyde, SDSPP Oct 2023target 2028
Onshore wind project GEN-2016-103, Hyde County
Onshore wind
240 MWWithdrawn / abandoned Hyde, SDSPP Nov 2016target 2018
Battery storage project GEN-2021-009, Beadle County
Battery storage
225 MWWithdrawn / abandoned Beadle, SDSPP May 2021target 2026
Solar + storage project GEN-2022-169, Hyde County
Solar + storage
220 MWWithdrawn / abandoned Hyde, SDSPP Feb 2023target 2027
Onshore wind project GEN-2020-018, Sully County
Onshore wind
205 MWWithdrawn / abandoned Sully, SDSPP Apr 2020target 2026
Battery storage project GEN-2017-199, Beadle County
Battery storage
202 MWWithdrawn / abandoned Beadle, SDSPP Nov 2017target 2026
Onshore wind project GEN-2018-129, Hyde County
Onshore wind
200 MWWithdrawn / abandoned Hyde, SDSPP Nov 2018target 2026
Onshore wind project GEN-2018-035, Clark County
Onshore wind
200 MWWithdrawn / abandoned Clark, SDSPP May 2018target 2021
Onshore wind project GEN-2024-059, Stanley County
Onshore wind
200 MWWithdrawn / abandoned Stanley, SDSPP Oct 2024target 2028
Onshore wind project GEN-2023-014, Mcpherson County
Onshore wind
200 MWWithdrawn / abandoned Mcpherson, SDSPP Oct 2023target 2026
Onshore wind project GEN-2017-098, Meade County
Onshore wind
200 MWWithdrawn / abandoned Meade, SDSPP May 2017target 2020
Onshore wind project GEN-2023-013, Mcpherson County
Onshore wind
200 MWWithdrawn / abandoned Mcpherson, SDSPP Oct 2023target 2026
Solar + storage project GEN-2023-098, Perkins County
Solar + storage
200 MWWithdrawn / abandoned Perkins, SDSPP Oct 2023target 2027
Solar project GEN-2023-154, Hand County
Solar
175 MWWithdrawn / abandoned Hand, SDSPP Oct 2023target 2029
Onshore wind project GEN-2016-092, Hyde County
Onshore wind
175 MWWithdrawn / abandoned Hyde, SDSPP Oct 20162020
Battery storage project GEN-2023-082, Brookings County
Battery storage
175 MWWithdrawn / abandoned Brookings, SDSPP Oct 2023target 2029
Solar project GEN-2018-007, Grant County
Solar
150 MWWithdrawn / abandoned Grant, SDSPP Apr 20182025
Solar project GEN-2020-093, Potter County
Solar
150 MWWithdrawn / abandoned Potter, SDSPP Apr 2020target 2026
Onshore wind project GEN-2019-060, Day County
Onshore wind
150 MWWithdrawn / abandoned Day, SDSPP May 20192025
Solar project GEN-2022-066, Perkins County
Solar
150 MWWithdrawn / abandoned Perkins, SDSPP Aug 2022target 2028
Onshore wind project GEN-2019-017, Butte County
Onshore wind
143 MWWithdrawn / abandoned Butte, SDSPP Apr 20192025
Onshore wind project GEN-2016-006, Haakon County
Onshore wind
140 MWWithdrawn / abandoned Haakon, SDSPP Mar 2016target 2018
Solar + storage project GEN-2023-066, Stanley County
Solar + storage
130 MWWithdrawn / abandoned Stanley, SDSPP Oct 2023target 2028
Onshore wind project GEN-2017-113, Bennett County
Onshore wind
119 MWWithdrawn / abandoned Bennett, SDSPP Oct 2017target 2021
Solar project GEN-2017-064, Oglala Lakota County
Solar
110 MWWithdrawn / abandoned Oglala Lakota, SDSPP May 2017target 2023
Onshore wind project GEN-2020-019, Tripp County
Onshore wind
108 MWWithdrawn / abandoned Tripp, SDSPP Apr 2020target 2027
Solar project GEN-2017-054, Lincoln County
Solar
102 MWWithdrawn / abandoned Lincoln, SDSPP May 2017target 2019
Solar project GEN-2019-006, Spink County
Solar
100 MWWithdrawn / abandoned Spink, SDSPP Apr 2019target 2022
Solar + storage project GEN-2023-084, Brown County
Solar + storage
100 MWWithdrawn / abandoned Brown, SDSPP Oct 2023target 2028
Onshore wind project GEN-2015-097, Day County
Onshore wind
100 MWWithdrawn / abandoned Day, SDSPP Oct 2015target 2016
Onshore wind project GEN-2023-012, Kingsbury County
Onshore wind
98.6 MWWithdrawn / abandoned Kingsbury, SDSPP Oct 2023target 2026
Solar + storage project GEN-2023-130, Potter County
Solar + storage
96.0 MWWithdrawn / abandoned Potter, SDSPP Oct 2023target 2027
Solar project GEN-2022-067, Meade County
Solar
85.0 MWWithdrawn / abandoned Meade, SDSPP Aug 2022target 2028
Battery storage project GEN-2019-032, Day County
Battery storage
63.1 MWWithdrawn / abandoned Day, SDSPP Apr 2019target 2020
Solar project GEN-2019-057, Day County
Solar
63.1 MWWithdrawn / abandoned Day, SDSPP Apr 2019target 2020
Battery storage project GEN-2019-040, Yankton County
Battery storage
60.0 MWWithdrawn / abandoned Yankton, SDSPP May 2019target 2021
Onshore wind project GEN-2023-067, Butte County
Onshore wind
41.0 MWWithdrawn / abandoned Butte, SDSPP Oct 2023target 2026
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)