United States βΊ Grid βΊ Interconnection queues βΊ South Dakota
SOLAR Β· SPPSolar project GEN-2020-093, Potter County
Solar project GEN-2020-093, Potter County is a 150 MW solar request withdrawn in the SPP interconnection queue, in Potter County, South Dakota, connecting to BEPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2020 (completed)
- Withdrawn / abandonedApr 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2020-093
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- BEPC
- Connection point (POI)
- Whitlock Substation 230 kV
- Location
- Potter County, South Dakota
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 April 2020
- Proposed online date
- November 2026
- Withdrawn
- April 2023
Location
Marker shows the centre of Potter County; the queue data does not give exact sites.
Power plants in South Dakota Β· Transmission lines in South Dakota
Other requests in Potter County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem