United States βΊ Grid βΊ Interconnection queues βΊ South Dakota
ONSHORE WIND Β· SPPOnshore wind project GEN-2023-013, Mcpherson County
Onshore wind project GEN-2023-013, Mcpherson County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Mcpherson County, South Dakota, connecting to BEPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedMar 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-013
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- BEPC
- Connection point (POI)
- Leland Olds to Groton 345 kV Line
- Location
- Mcpherson County, South Dakota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- December 2026
- Withdrawn
- March 2024
Location
Marker shows the centre of Mcpherson County; the queue data does not give exact sites.
Power plants in South Dakota Β· Transmission lines in South Dakota
Other requests in Mcpherson County
- Onshore wind project J3420, Mcpherson CountyOnshore wind Β· 200 MW Β· in study
- Onshore wind project J3428, Mcpherson CountyOnshore wind Β· 200 MW Β· in study
- Onshore wind project T32, Mcpherson CountyOnshore wind Β· 2,500 MW Β· withdrawn
- Onshore wind project T34, Mcpherson CountyOnshore wind Β· 1,500 MW Β· withdrawn
- Onshore wind project T33, Mcpherson CountyOnshore wind Β· 1,000 MW Β· withdrawn
- Coal project GI-0111a, Mcpherson CountyCoal Β· 750 MW Β· withdrawn
- Onshore wind project J1621, Mcpherson CountyOnshore wind Β· 400 MW Β· withdrawn
- Onshore wind project GEN-2023-014, Mcpherson CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J2338, Mcpherson CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J2333, Mcpherson CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project G296, Mcpherson CountyOnshore wind Β· 25.0 MW Β· withdrawn
- Solar + storage project J1738, Mcpherson CountySolar + storage Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem