ONSHORE WIND Β· MISOOnshore wind project G296, Mcpherson County
Onshore wind project G296, Mcpherson County is a 25.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Mcpherson County, South Dakota.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2003 (completed)
- Withdrawn / abandonedApr 2003 (project stopped here)
- ConsentedApr 2003 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G296
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Mcpherson County, South Dakota
- Technology
- Wind: 25.0 MW
- Total requested
- 25.0 MW
- Queue status
- Withdrawn
- Entered queue
- 10 February 2003
- Agreement signed
- 1 April 2003
- Proposed online date
- June 2009
- Withdrawn
- April 2003
Location
Marker shows the centre of Mcpherson County; the queue data does not give exact sites.
Power plants in South Dakota Β· Transmission lines in South Dakota
Other requests in Mcpherson County
- Onshore wind project J3420, Mcpherson CountyOnshore wind Β· 200 MW Β· in study
- Onshore wind project J3428, Mcpherson CountyOnshore wind Β· 200 MW Β· in study
- Onshore wind project T32, Mcpherson CountyOnshore wind Β· 2,500 MW Β· withdrawn
- Onshore wind project T34, Mcpherson CountyOnshore wind Β· 1,500 MW Β· withdrawn
- Onshore wind project T33, Mcpherson CountyOnshore wind Β· 1,000 MW Β· withdrawn
- Coal project GI-0111a, Mcpherson CountyCoal Β· 750 MW Β· withdrawn
- Onshore wind project J1621, Mcpherson CountyOnshore wind Β· 400 MW Β· withdrawn
- Onshore wind project GEN-2023-014, Mcpherson CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J2338, Mcpherson CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2023-013, Mcpherson CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J2333, Mcpherson CountyOnshore wind Β· 200 MW Β· withdrawn
- Solar + storage project J1738, Mcpherson CountySolar + storage Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem