United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· SPP

Onshore wind project GEN-2018-129, Hyde County

Onshore wind project GEN-2018-129, Hyde County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Hyde County, South Dakota, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2018 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-129
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Fort Thompson-Oahe 230kV
Location
Hyde County, South Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
19 November 2018
Proposed online date
October 2026
Withdrawn
December 2022

Location

Marker shows the centre of Hyde County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Hyde County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem